On an Alberta Infrastructure project, the security you have to post is set at 50% of the contract price, and you have 15 days from the letter of acceptance to produce it. That is the whole requirement in one sentence, and it is the part most concrete scopes get right.
What goes wrong is everything around it. The security package is not the same at every contract value, the cheapest-looking option freezes your money for a year past completion, and the form edition named in your contract is part of the requirement. After 38 years pouring concrete in this city, we have watched more bids go sideways between the letter of acceptance and the first truck than during the pour itself.
Here is how contract performance security works on an Alberta job, and where a concrete scope sits inside it.
The baseline requirement is 50% of the contract price, not the whole job
A performance bond does not cover the full value of the work. Alberta Infrastructure’s Basic Master Specification, Section 00 61 13 Contract Performance Security, requires a “Performance Bond for 50% of the Contract Price.” That single number resolves the most common misread we hear on the phone, which is that a bonded job ties up security equal to the contract.
Three more requirements travel with it in the same section:
- The form is named. The bond must be on the “Canadian Construction Documents Committee (CCDC) Standard Form of Performance Bond, CCDC Document No. 221.”
- The surety must be licensed here. It has to be a “duly incorporated surety company authorized to transact business of suretyship in the Province of Alberta.” A surety that writes in another province and not in Alberta does not satisfy the clause.
- The clock is 15 days. Security is submitted “within 15 Days after date of issuance of Letter of Acceptance of bid,” and the bond is consigned to “His Majesty the King in right of Alberta, as represented by the Minister of Infrastructure.”
Fifteen days sounds generous until you remember that underwriting is not instant and a surety will want current financial statements. Open that conversation while you are pricing, not after you win.
The bonding line sits around $100,000, but the contract documents govern
Bonding is normally triggered at a six-figure contract value, and the guidance is explicit about it. The Basic Master Specification tells the specifier to “normally specify contract performance security when estimated contract cost is $100,000.00 or greater.” The Small Projects Master Specification repeats the department’s policy the same way, describing bonding on contracts whose estimated value is “$100,000 or greater.”
Read that wording carefully. The $100,000 figure is drafting guidance aimed at the person writing the specification, not an obligation worded to attach to you as a bidder. What binds you is whichever security section ends up in the contract documents you signed.
The practical rule we work to: assume security at or above roughly $100,000, confirm it against the issued specification section, and never carry the assumption over from the last job. Which brings us to the part that surprises people.
The small-projects band carries a different package entirely
The security package changes with contract size, and the smaller band is in some ways heavier. Alberta Infrastructure’s Small Projects Master Specification applies to contracts with an estimated cost “between $100,000.00 and $250,000.00 inclusive,” and it asks for two bonds rather than one, while also offering two cash substitutes the regular specification does not.
| Requirement | Basic Master Specification (regular projects) | Small Projects Master Specification ($100,000–$250,000) |
|---|---|---|
| Performance bond | 50% of the contract price, CCDC 221 | 50% of the contract price, CCDC 221 |
| Labour and material payment bond | Not specified in the section | 50% of the contract price, on Government of Alberta form 00 61 90B-A eForm |
| Certified cheque or bank draft option | None offered | 10% of the contract price |
| Irrevocable letter of credit option | None offered | 10% of the contract price |
| Deadline | 15 days after the letter of acceptance | 15 days after the letter of acceptance |
| Surety | Authorized to transact suretyship in Alberta | Authorized to transact suretyship in Alberta |
So a $180,000 concrete package can land with a two-bond requirement, while a $2,000,000 package carries a single performance bond under the section that governs it. That is the opposite of what most people assume, and it is why the security section is worth reading before the bid closes.
The letter of credit option carries one more condition: it must come from a chartered bank listed under the Bank Act (Canada) or from ATB Financial, and it expires one year after the contract completion date.
The 10% option is usually the expensive one
If you have the choice, the cash and letter of credit options are the costly route, and the arithmetic makes the case better than any argument.
Take a $200,000 concrete contract in the small-projects band. A certified cheque or bank draft at 10% means $20,000 of your own money leaves the business and does not come back until the owner releases it. An irrevocable letter of credit at the same 10% does not move the cash, but it occupies a line with your bank, and it stays occupied until one year after contract completion. A bond, by contrast, is underwritten against your balance sheet and your track record instead of against today’s cash.
That distinction compounds. Bond capacity behaves like a credit limit: it is finite, and the work already on your books consumes it. Tie up $20,000 in a cheque, or a chunk of your bank line, and you have quietly reduced what you can bid on the next three jobs.
The security decision is a cash-flow decision wearing paperwork’s clothes. Treat it as one.
What the labour and material payment bond actually does, and who can claim on it
A labour and material payment bond does not protect you. It protects the people below you, which is exactly why owners ask for it on the smaller band where supply chains are thinner.
The federal standard form is the clearest public statement of how these bonds operate, and it is worth reading even on provincial work. Public Services and Procurement Canada’s Labour and Material Payment Bond, form PWGSC-TPSGC 506, defines a claimant as “one having a direct contract with the Principal or any Sub-Contractor of the Principal” who supplied labour, material or services used or reasonably required for the contract. Parties with no direct contract with the principal are limited separately.
The clocks in that form are short and unforgiving:
- Written notice of a holdback claim must be given “within one hundred and twenty (120) days after such Claimant should have been paid in full under this Contract.”
- Written notice of other claims runs on the same 120-day period, measured from the date the claimant last performed.
- No suit may be commenced “after the expiration of one (1) year following the date on which the Principal ceased work,” including work under contract guarantees.
- A claimant unpaid “before the expiration of a period of ninety (90) days” after its last labour, service or materials opens the door to action on the bond.
One caution on jurisdiction: form 506 is the federal form, while an Alberta Infrastructure small-projects contract calls for the Government of Alberta form, 00 61 90B-A eForm. The structure is familiar across these bonds, but the operative wording and periods are whatever your form says. Confirm the form named in your contract before relying on a number from a different one.
The form edition is part of the requirement
The bond edition is not a formality, and 2024 moved the goalposts. The Canadian Construction Association confirms that the CCDC bond forms were reissued in 2024: CCDC 220 Bid Bond, CCDC 221 Performance Bond and CCDC 222 Labour & Material Payment Bond. The new editions “have been updated to incorporate the Ready-for-Takeover project milestone and introduce further clarity, collaboration, and responsiveness on the part of the surety.”
Alberta’s Basic Master Specification section carries a 2022 date and names CCDC 221 without specifying an edition. That is a question to settle with the owner, not with your surety, because the milestone language in the newer edition interacts with when the bond’s obligations are measured. Ask which edition the contract documents require, get the answer in writing, and order that one.
Where a concrete subcontract sits in all of this
Everything above runs from the owner to the prime contractor. A concrete scope usually sits one level down, which changes the requirement completely: bonding on a subcontract is almost never statutory or policy-driven. It is a commercial term the general contractor chooses to impose, with three consequences worth planning around:
- It has to be priced, not assumed. A bond requirement discovered after the number is submitted comes out of margin. It belongs on the quote as a line, like every other cost of carrying the work — see what should be itemised on a concrete quote.
- You may be a claimant rather than a principal. Where the prime has posted a labour and material payment bond, a concrete subcontractor or its suppliers can fall squarely inside the claimant definition, on the notice periods above. That is a remedy worth knowing before it is needed.
- It is separate from the holdback. Security and statutory holdback are different mechanisms with different triggers and calendars. Posting a bond does not change what the owner retains, and the holdback timing has its own trap, which we cover in Alberta’s holdback and prompt payment rules.
Who carries which safety obligation on a multi-employer site is a separate question, and we set out the designation rules in prime contractor requirements in Alberta.
Settle these six items before you sign
- Which security section is in the issued contract documents, and which contract-value band it belongs to.
- Whether a labour and material payment bond is required in addition to the performance bond.
- Which form and which edition the owner requires for each bond.
- Whether a cash or letter of credit substitute is offered, and whether taking it is cheaper than the premium once you price the frozen capital.
- Whether your surety is authorized to transact suretyship in Alberta.
- What your remaining bond capacity is after the work already on your books, before you commit it to this job.
FAQ
Is a performance bond required on every Alberta construction contract? No. Alberta Infrastructure’s guidance is to specify contract performance security normally when estimated contract cost is $100,000.00 or greater. Otherwise, bonding is whatever the contract documents require.
How much is an Alberta performance bond for? Both the Basic Master Specification and the Small Projects Master Specification set the performance bond at 50% of the contract price, on CCDC Document No. 221.
How long do I have to provide the bond after winning? Fifteen days after the date the letter of acceptance of bid is issued, under both specifications.
Can I post cash instead of a bond? On a small-projects contract between $100,000.00 and $250,000.00 inclusive, yes: a certified cheque or bank draft at 10%, or an irrevocable letter of credit at 10% from a chartered bank listed under the Bank Act (Canada) or from ATB Financial, expiring one year after contract completion. The regular specification offers no substitute.
Does a performance bond cover unpaid subcontractors and suppliers? No. That is the function of a labour and material payment bond, which is a separate instrument with its own form and its own notice periods.
Do concrete subcontractors need to be bonded? Not by statute. A subcontract bond is a commercial requirement a general contractor may impose, so it should be confirmed and priced before the number goes in.
Where this article stops
This page covers the security the owner requires and what each instrument does to your cash. It does not cover bond premium pricing or surety underwriting criteria, bid bonds and tender security mechanics, CCDC prime contract administration, the statutory holdback and prompt payment calendar, the bonding policies of municipalities and private owners, or insurance such as commercial general liability and builder’s risk.
Talk to us before the letter of acceptance lands
Security is cheap to get right early and expensive to fix late. If you are scoping a concrete package likely to cross the bonding line, the useful conversation happens while the estimate is still open, when the band, the forms and your capacity can all still change the number you submit.
Reach our commercial concrete contractors in Calgary to walk through a scope before it goes out.
Sources
- Alberta Infrastructure, Basic Master Specification, Section 00 61 13 Contract Performance Security: https://www.alberta.ca/system/files/custom_downloaded_images/tr-00-61-13b.pdf
- Alberta Infrastructure, Small Projects Master Specification, Section 00 61 13SP: https://www.alberta.ca/system/files/custom_downloaded_images/00-61-13sp.pdf
- Canadian Construction Association, new CCA and CCDC documents now available: https://www.cca-acc.com/plus/new-cca-and-ccdc-documents-now-available/
- Public Services and Procurement Canada, Labour and Material Payment Bond, PWGSC-TPSGC 506: https://www.canada.ca/en/public-services-procurement/services/acquisitions/forms/labour-material-payment-bond-506.html