There is a hard clearance number between your placing boom and the overhead line at the back of the lot, and it is not a number you are allowed to decide. Alberta’s Occupational Health and Safety Code sets it by the operating voltage of the line, and you cannot read operating voltage off a conductor from the ground. That one fact reorganizes the whole sequence: before the distance means anything on your site, somebody at the utility has to tell you what the line is carrying. Until they do, the Code hands you a single default number and holds you to it.
What follows is the sequence we run on commercial sites in this city, in the order the Code imposes it, with the two phone calls separated because they are two different obligations with two different triggers.
The default distance is 7 metres, and it holds until the utility verifies the voltage
Section 225(1) of the OHS Code is the trigger, and it is distance-based, not activity-based. Once work or equipment operation will happen within 7 metres of an energized overhead power line, the employer must contact the operator of that line to determine its voltage. The Part 17 explanation guide published by the province states the consequence plainly: “Until the power line operator verifies the voltage, the employer must maintain a safe clearance distance of 7 metres.”
Read that as a default, not as a penalty. Seven metres is the distance that applies to the highest-voltage transmission line in the Schedule, so the Code assumes the worst line until somebody with records says otherwise. On a tight infill lot with a boom pump, 7 metres is often the difference between reaching the far corner of the footing and not reaching it at all. The call that converts 7 metres into 3 metres is a scheduling task, not a safety formality.
Schedule 4 sets the distance by voltage, and the steps are coarse
Schedule 4 of the OHS Code lists the safe limit of approach distance for persons and equipment against the operating voltage between conductors. The distances are drawn from Alberta’s Electrical and Communication Utility Code, 2nd Edition, 2002.
| Operating voltage between conductors | Safe limit of approach distance |
|---|---|
| 0 to 750 volts, insulated or polyethylene covered conductors | 300 millimetres |
| 0 to 750 volts, bare or uninsulated | 1.0 metre |
| Above 750 volts, insulated conductors | 1.0 metre |
| 750 volts to 40 kilovolts | 3.0 metres |
| 69 kilovolts to 72 kilovolts | 3.5 metres |
| 138 kilovolts to 144 kilovolts | 4.0 metres |
| 230 kilovolts to 260 kilovolts | 5.0 metres |
| 500 kilovolts | 7.0 metres |
Two details on this table decide more site arguments than the numbers themselves. The insulated rows only apply where the conductors are insulated or covered throughout their entire length, and manufactured to rated and tested insulation levels – a conductor that looks covered where you are standing does not qualify. And the 750 volt to 40 kilovolt row, at 3.0 metres, covers nearly every distribution line running down a residential lane or along a collector road in Calgary. Most of the time the answer to the call is 3 metres. You still do not get to assume it.
Two calls, two triggers, and only one of them is about information
The Code splits the utility relationship in half, and crews conflate the halves constantly.
The first call is informational and is triggered by the 7 metre proximity under section 225(1). You are asking what the line carries so you can apply the right row of Schedule 4. Nothing about the work changes as a result of this call except the number.
The second call is a notification and is triggered by intent. Under section 225(2), if the work genuinely must happen closer than the Schedule 4 distance, the employer must notify the operator of the power line before the work begins, and obtain its assistance in protecting workers. The operator may de-energize the line, relocate it, isolate it, or take another equally effective action. Section 225(1.1) is the clamp that makes this matter: the Schedule 4 distance is a limit at all times, and no worker or equipment comes closer than it unless the operator has given permission and assistance under 225(2).
In practical terms, there is no version of this where a superintendent decides the clearance is tight but acceptable. The distance is either respected, or the line has been dealt with by its owner.
In Calgary, the first call has a phone number
ENMAX’s project safety guidance tells anyone working within seven metres of an overhead power line to call its Power Trouble line at 403-514-6100 for advice on how to work safely, and states that where ENMAX determines it is needed, a crew will attend and turn the power off until the task is complete.
Put that number in the pre-pour package, not in somebody’s phone. The lead time on a de-energization or a temporary line guard is a real schedule input, and it belongs on the same page as the concrete order and the pump booking. We have watched more pours slip on an unmade utility call than on a late truck.
The transport exemption does not cover equipment working on your site
Section 226 is where sites get caught. The Schedule 4 distances do not apply to loads, equipment, or buildings less than 4.15 metres in height while they are being transported beneath an energized overhead power line. That exemption is about passing under a line, and nothing else.
The distances continue to apply when equipment moves about a worksite during the work – a crane repositioning between picks, a boom pump swinging to a second placement, a telehandler tracking along a footing. Driving a machine under a line on the access route and then operating that same machine on the slab are two different regulatory situations with the same machine. Section 227 carves out electric utility workers, qualified electric utility workers, and electric utility tree trimmers, who work to distances set in the utility code instead. Nobody on a concrete crew is inside that exemption.
A spoil pile can take your clearance away
Section 225(3) states that piles of earth or other materials beneath or beside a power line must not reduce the safe limit of approach distances. Clearance is measured from the surface the equipment and workers are standing on, so stockpiling the excavation under the line lifts the working surface and shortens the gap by exactly the height of the pile.
This is the quiet one, because the pile usually arrives on a day when nobody is working near the line. Where the only sensible place for spoil is the side of the lot under the overhead, that is a stockpile location decision made at the excavation stage, and it belongs in the same conversation as haul-off and clean fill. The same logic governs where formwork bundles, rebar, and panel stacks get laid down.
The signaller has one job, and it is narrower than people assume
Where a signaller is used, the province’s guidance points to a competent signaller as described in section 191 of the OHS Code, and defines the role tightly: the signaller’s only responsibility is to make sure the equipment operator does not get closer than the safe limit of approach distance.
That is not a spotter who also watches the pour, directs trucks, and screeds. Assigning the signaller a second task is how the first task stops happening. The guidance also warns against relying on devices such as hook insulators or insulating blankets as the control – those are supplements, not the clearance.
What goes on the pre-pour checklist
After 38 years pouring concrete in this city, we have sat through enough pre-pour meetings to know which items get handled and which get assumed. The overhead line is almost always in the assumed column. Five entries move it out:
- Mark every overhead line crossing the lot or the lane on the site plan, with the voltage the utility confirmed and the Schedule 4 distance that follows from it.
- Record who at the utility confirmed the voltage, and when. The number is only as good as its source.
- Decide, at the layout stage, whether the boom reach plan requires work inside the Schedule 4 distance. If it does, that is a section 225(2) notification with lead time, not a day-of decision.
- Fix the spoil and material laydown locations so nothing raises the working surface under a line.
- Name the signaller, and give that person nothing else to do during the lift or the placement.
The same discipline we apply to the numbers in footing depth and to the dimensional requirements behind accessible parking stalls applies here. A clearance is a dimension. It gets surveyed, recorded, and signed off, or it gets argued about after a contact.
FAQ
How close can a concrete pump boom get to an overhead power line in Alberta? No closer than the Schedule 4 distance for that line’s operating voltage, and no closer than 7 metres until the line’s operator has verified the voltage. For a typical distribution line in the 750 volt to 40 kilovolt band, the distance is 3.0 metres.
Who is responsible for determining the voltage of the line? The employer. Section 225(1) places the duty to contact the power line operator on the employer, and the operator supplies the voltage.
Can we work inside the safe limit of approach distance if we are careful? No. Section 225(1.1) makes the Schedule 4 distance a limit at all times. Working closer requires notifying the operator before the work begins and obtaining its assistance under section 225(2).
Does the covered line behind the lot count as insulated? Only if the conductors are insulated or covered throughout their entire length and manufactured to rated and tested insulation levels. Appearance at one point along the span is not the test.
Do the distances apply while we drive equipment under the line to get to the pour? Loads, equipment, and buildings under 4.15 metres in height are exempt while being transported beneath the line. Once the machine is working on the site, the distances apply again.
Talk to us before the layout stakes go in
Clearance problems are cheap to solve at layout and expensive to solve the morning of the pour, because by then the boom position, the truck route, and the spoil pile are all already committed. If you have a commercial pour with an overhead line anywhere near the reach envelope, bring us in while the site plan is still a drawing. See what we handle on commercial concrete projects in Calgary, or send us the site plan and the line locations and we will tell you where the reach plan and the Schedule 4 distance disagree. Tolerances that get settled on paper, the way exterior slope tolerances do, stay settled.
Sources
- Alberta Occupational Health and Safety Code, Schedule 4: Safe Limit of Approach Distances – https://search-ohs-laws.alberta.ca/legislation/occupational-health-and-safety-code/schedule-4-safe-limit-of-approach-distances/
- Government of Alberta, Occupational Health and Safety Code Part 17 Explanation Guide: Overhead Power Lines – https://open.alberta.ca/dataset/757fed78-8793-40bb-a920-6f000853172b/resource/d8420e31-073c-43d1-b6ef-c72daee55d71/download/4403880-part-17-overhead-power-lines.pdf
- ENMAX, Project Safety – https://enmax.com/outages-and-safety/safety-guidelines/project-safety