The perimeter is the one part of a construction site built before anything else and priced after everything else. It is also the only part a member of the public can walk up to and test. On a foundation job that puts an open excavation two metres from a sidewalk, the fence is not site furniture. It is a code requirement with a height, a surface, a locking rule, a sign, and a named party who answers for it. In Calgary three documents assign that party differently, and two cite instruments since replaced.
The short answer, before the detail
Where a construction or demolition activity may be a hazard to the public and the work is two metres or more from a public way, Part 8 of the building code requires a strongly constructed fence, boarding or barricade not less than 1.8 metres high. Access openings must be gated, and those gates must be kept closed and locked whenever the site is unattended. The fencing goes up before work starts and stays until the work is finished.
The trigger is distance from the public way, not the size of the job
The requirement is written against the public, not against the contract value. Calgary’s advisory bulletin puts it directly: fencing is required at construction sites, demolition sites, sites where emergency construction work is performed, and any area the authority having jurisdiction considers unsafe. The practical test it adds is whether the public may reasonably be expected to be near the work. There is no square-footage threshold and no exemption for a job that takes a week, because the governing variable is proximity, not scale.
The Regional Municipality of Wood Buffalo, writing more recently on the same article, is blunter about timing: fencing must be fully in place before work starts, and must stay up until debris is removed and the site is graded so it cannot hold water. That clause means the perimeter outlasts the pour, the strip and the backfill.
The number survived the code change; the citations on Calgary’s own pages did not
The National Building Code 2023 Alberta Edition came into force on May 1, 2024, and the Alberta Safety Codes Council publishes update resources for it, including an Alberta Municipal Affairs comparison document covering Part 8.
Calgary’s fencing advisory is dated April 2016 and cites the 2014 Alberta Building Code: Division B, Articles 8.2.1.3, 8.2.1.4 and 8.2.1.5, and Division C, Article 2.2.14.2. The Calgary Construction Site Guide is dated December 2016 and cites the same Division B article together with Community Standards Bylaw 5M2004 and the Street Bylaw. The Wood Buffalo bulletin, written for the 2026 season, cites Article 8.2.1.3, Fencing, Boarding or Barricades, in the 2023 Alberta Edition, and gives the same two numbers.
So two Alberta authorities, working from two different code editions, land on the same height and the same trigger. The requirement is stable; the citation is not. Use Calgary’s documents for what the City expects on a site, and confirm article and section numbers against the edition in force before you quote them in a submittal or a dispute. After 38 years pouring concrete in this city, we have found that nobody argues about the fence until there is a claim, and then everybody argues about which clause applied.
Whose fence it is: three instruments, three answers
Ask who owns the perimeter and you get three defensible answers.
| Instrument | Who it names | What it says |
|---|---|---|
| Division C, 2.2.10.9.(1) and (2) | The owner | The owner must carry out the work, or have it carried out, in accordance with the Safety Codes Act, the code and the permit, and must ensure all activities on the site meet the requirements |
| Division C, 2.2.14.1.(2) | The owner and the contractor | The contractor and the owner are fully and equally responsible for safety during construction, and section 5.3 of the Calgary Construction Site Guide reads Article 2.2.14.1 as making the contractor responsible for compliance with Part 8 |
| Occupational health and safety framework | The prime contractor | Where a site has two or more employers, a prime contractor is required and is responsible for coordinating health and safety at the work site |
Calgary’s fencing advisory does not mention prime contractors at all. It treats the owner as responsible for the construction, maintenance, care and control of the site, and notes the owner is often also the contractor. The Wood Buffalo bulletin says owners and contractors are responsible for securing the work area with their own fencing, anchored in Part 1, section 5 of the Safety Codes Act, which puts a duty on the owner of a thing, process or activity.
We are not going to average these into one answer, because they are not describing the same thing. The code assigns the construction duty, the guide assigns Part 8 compliance, and the occupational health and safety framework assigns coordination among employers. A single site can have all three live at once, pointing at three different companies. So this is a contract question: name the party that supplies, installs, inspects and locks the perimeter, and name who re-secures it after hours, in writing, before anyone mobilizes. Our note on the designation itself is at prime contractor requirements in Alberta.
What the barricade itself has to be
The code does not simply ask for a fence. It describes one.
- Height. Not less than 1.8 metres between the site and the public way.
- Surface. A reasonably smooth surface facing the public way.
- Openings. Without openings, except those required for access.
- Gates. Access openings equipped with gates, kept closed and locked when the site is unattended, and maintained in place until the construction or demolition activity is complete.
- Materials. Calgary’s advisory states that snow fencing is not an acceptable material. Wood Buffalo accepts standard 1.8 metre steel panels where they are wired together and braced so they are stable and not easily bypassed, and sends anything else to a Safety Codes Officer for case-by-case review.
Two of those bullets do most of the failing, and both are visible from the street without anyone entering the site: a chain-link panel run is not a reasonably smooth surface facing the public, and a gate that is chained but not locked is not locked.
Openings within three metres of grade get their own rule
Separate from the perimeter, the code addresses what happens when work stops. Openings within three metres of ground level must be covered with a securely fastened barricade, or the hazardous area must be fenced to the same 1.8 metre standard. On concrete work that catches the predictable items: a stripped stairwell, a penetration cut through a slab, an elevator pit, a cored opening left for a trade arriving next week. It also catches the excavation, which is a different obligation from the one protecting your own crew inside the hole, covered in excavation shoring requirements in Calgary.
There is also a provision most estimators have never had to price: where protection by other means is not possible, persons shall be employed to prevent the public from entering the danger zone at any time of the day or night. That is a staffing line, and it is why a crane pick over a live sidewalk is never only equipment cost.
When the fence leaves your property, it becomes a permit
The moment the perimeter occupies street, sidewalk or boulevard, you are in a different process. Calgary’s hoarding permit requirements, dated February 2017, ask for a project description, a justification for using the street, the off-street alternatives you considered and why you rejected them, and a full schedule of hoarding dates and hours. They also require engineered drawings with detailed notes, signed and stamped by an engineer, with dimensions certified as accurate. Other items in that package are easy to miss until they hold up an application:
- Screening is to be solid white fencing as a minimum, with decorative or artistic screening recommended.
- Safe pedestrian passage must be provided at all times past the site, with cyclists, children and people with special needs considered. Hoisting that poses a hazard which cannot be protected shall not be carried out until the sidewalk or boulevard is closed, and only the Traffic Engineer can permit that closure.
- Closures are allowed only where it is established that no reasonable alternative exists.
- The 7.5 metre triangular area at corners is to remain free of all material.
- Construction information signage is to be posted on the hoarding fence.
- A Tree Protection Plan under Bylaw 23M2002 may be required, along with transit approval, a traffic impact study and a public communication plan.
- Permit cost is calculated from the street, sidewalk or boulevard space identified. No processing time is stated anywhere in the document, which is the most useful thing to know: build float.
The sign is a code item, not a courtesy
Sites that require security fencing must post a sign where the building or demolition permit is issued, and the Calgary Construction Site Guide is specific: the sign must be legible and include a clearly identifiable company name, phone numbers and email. That requirement is carried by the Building Permit Bylaw, and if an owner or contractor has no acceptable sign, Building Regulations provides one with the permit. The Guide separately recommends, as best practice, appointing a community liaison and putting their contact information on the signage. That is not the same obligation, and the two often get merged into one line on a submittal.
The housekeeping obligations that ride along with the perimeter
The Guide attaches a short set of site-conduct duties to the same boundary: airborne dust or debris must not leave the site; sidewalks, roads and boulevards must be kept free of debris; surface drainage must not reach adjacent properties and surface water must not accumulate; and outdoor light must not shine into the windows of adjacent dwellings.
Two cautions. The Guide cites those duties to Community Standards Bylaw 5M2004, since replaced by a later consolidation, so treat the obligations as current and the section numbers as needing a check. The Guide also says to remove any vehicle parked in an unapproved location within 30 minutes of a complaint, citing the Street Bylaw, but it does not make clear whether that figure is a requirement or a recommended practice. Plan for 30 minutes and ask the City which it is.
Debris leaving the site is where tear-out becomes a bylaw problem rather than a disposal problem. Our note on the disposal side is at concrete removal and disposal in Calgary.
What happens if the site is found open
A Safety Codes Officer may require a hazardous site to be secured immediately, which can mean full or partial fencing, or reinstalling fencing that already exists. The owner is contacted first; if the owner is unavailable, the advisory states that the officer will carry out orders to secure the site at the owner’s expense. That is the cost nobody budgets: not a fine, but an invoice for work ordered on your behalf, on a weekend, by someone not shopping the price.
Where this article stops
This article is about the perimeter and the public. It does not cover traffic accommodation inside a road right-of-way, a separate approval stream with its own drawings and lead time, or protection of your own workers inside an excavation, which carries different numbers. It does not interpret which article number applies under the edition now in force.
Talk to us before the excavator is booked
The perimeter decides your mobilization sequence, not the other way round. If the fence cannot go up before the dig, the dig moves. Send us the site plan and the setback from the public way and we will tell you where the perimeter lands and what it does to access and lay-down. Start at our Calgary foundations page.
FAQ
How high does a construction site fence have to be in Calgary? Not less than 1.8 metres between the site and the public way, where the activity may be a hazard to the public and is two metres or more from a public way.
Is chain-link or snow fencing acceptable? Calgary’s advisory states that snow fencing is not acceptable. The code also requires a reasonably smooth surface facing the public way and no openings except those needed for access.
Do the gates have to be locked? Yes, closed and locked whenever the site is unattended, and maintained until the activity is complete.
Who is responsible, the owner or the contractor? Both, depending on which instrument you read, and a prime contractor may carry coordination duties as well. Name the responsible party in the contract.
Sources
- City of Calgary, Advisory Bulletin: Construction Site Fencing, April 2016: https://www.calgary.ca/content/dam/www/pda/pd/documents/building/advisories/br-advisory-construction-site-fencing.pdf
- City of Calgary, Calgary Construction Site Guide, December 2016: https://www.calgary.ca/content/dam/www/pda/pd/documents/inspections/practical-guide-for-construction-sites.pdf
- City of Calgary, Hoarding Permit Application Requirements, February 2017: https://www.calgary.ca/content/dam/www/transportation/roads/documents/traffic/permits/hoarding-permit-application-requirements.pdf
- Regional Municipality of Wood Buffalo, Fencing During Construction and Demolition: https://www.rmwb.ca/media/bavj3erw/fencing-during-construction-demolition-2026.pdf
- Alberta Safety Codes Council, National Building Code 2023 Alberta Edition code update requirement resources: https://safetycodes.ab.ca/for-safety-codes-officers/code-updates/national-building-code-2023-alberta-edition-code-update-requirement-resources/