An adhesive anchor is the only structural connection on your job whose capacity is created after the design is finished. A cast-in bolt is either in the right place or it is not. An adhesive anchor is a hole, a cleaning method, a cartridge with a date on it, an orientation and a cure — every one of those a field variable. Get the cleaning wrong and the number on the drawing is fiction, with nothing visible to show it.
CSA A23.3 grades the inspection an anchor gets by how badly a bad installation would end, and for one case it asks for a witness on site and a load test on finished work. After 38 years pouring concrete in this city, we can tell you the anchors that come back on a project are almost never the ones an engineer sized wrong. They are the ones nobody watched.
The short answer: orientation and sustained tension decide everything
Two questions set the inspection level. Is the anchor horizontal or upwardly inclined, so the adhesive holds against gravity while it cures and for the life of the structure? And is it resisting sustained tension — a load permanently there rather than one that comes and goes?
If both answers are yes, the Canadian standard asks for continuous special inspection and proof loading. Everything else gets periodic inspection. That is the whole decision tree, and it belongs in the conversation before drawings are issued.
| Anchor condition | Inspection required |
|---|---|
| Adhesive anchors and post-installed rebar, horizontal or upwardly inclined, resisting sustained tension | Continuous special inspection and proof loading |
| Adhesive anchors and post-installed rebar, any other orientation or loading | Periodic special inspection |
| Mechanical anchors | Periodic special inspection |
The clause is CSA A23.3 Annex D. The standard is paywalled, so the figures below come from published summaries of it and from the American documents the clause is built on. We flag which is which throughout, and your engineer’s copy governs any clause number you quote in a specification.
Both levels are defined terms, not adjectives. Continuous means present when and where the inspected work is performed; holes may still be drilled while the inspector is away, provided the bits used and the hole diameter are verified afterwards. Periodic means intermittently present — but the first installation of each anchor type and size by each crew must be observed, so the visit is timed to the start of the work.
What a proof load proves, and what it does not
A proof load verifies installation quality and bond development. It is explicitly not a measurement of ultimate strength, and the Canadian clause carries a note that proof loading is not a substitute for special inspection. You do both, or you have done neither.
The published values for the Canadian clause:
- The proof load is the lesser of a bond-governed and a steel-governed value.
- Bond-governed: 67 per cent of the characteristic bond resistance associated with uncracked concrete, adjusted for edge distance and concrete strength, based on the individual anchor being loaded with no group effects.
- Steel-governed: not more than 80 per cent of the minimum specified yield strength of the anchor steel.
- Hold the load a minimum of 10 seconds, in a confined test setup in accordance with ASTM E3121, and only after the adhesive has fully cured per the manufacturer’s published installation instructions.
- Equipment is calibrated by an independent qualified third party, and the testing program and its parameters belong in the contract documents.
A divergence worth knowing about. The American guidance this practice grew out of gives the same two percentages, but asks for a hold of at least 15 seconds and expresses the steel limit against nominal yield rather than minimum specified yield. We are not going to average those. On an Alberta project the Canadian standard governs, and the hold time in your procedure should be the one your specification names. If it names neither, close that gap at submittal review, not on the day of the test.
The percentage nobody specified
This is the gap that costs the most money, and it is not technical. The American guidance publishes sampling rates: a minimum of 5 per cent random testing for redundant or less critical work, typically 10 to 20 per cent on large projects, 50 per cent for certain healthcare authorities, and all anchors where only a few are involved. The Canadian clause publishes no rate. It puts the testing program and its parameters in the contract documents.
Read that plainly: in Alberta, if nobody wrote a percentage into the contract documents, nobody has specified one. We have watched that discovery arrive with the crew demobilised and an engineer asked to invent a test program after the fact. Ask at the pre-construction meeting, where the answer is free.
The same clause expects a remediation plan in the contract documents for an anchor that fails — determined by the licensed design professional, typically some combination of testing more anchors, evaluating or replacing the anchor, and adding anchors. Unwritten, one failed anchor stops the work while three parties negotiate.
Who is allowed to be the inspector
Inspection is performed by a third-party inspector, or by a person employed by the owner or the owner’s representative who holds the necessary competence. The American guidance is blunter and it catches contractors out: the owner, or the engineer or architect of record acting as the owner’s agent, employs the special inspector — the contractor does not, unless the contractor is also the owner. It adds a point that saves arguments: an engineering degree or licence does not automatically qualify someone, because the qualification is inspection experience plus practical experience in the work itself. For the horizontal and upwardly inclined sustained-tension case, the American code also requires certified installers.
The checklist the inspector is running
Hand this to your foreman. Every item is something your crew controls, and the published task lists converge on them:
- Drilling method, bit type and bit size — design bond strength depends on the roughness the specified method produces.
- Hole diameter and depth, verified before installation, and edge distance and spacing against the contract documents.
- Hole cleaning per the manufacturer’s published installation instructions, with water and concrete-particle slurry removed. Holes cleaned in advance must be confirmed protected from contaminants and moisture.
- Adhesive identification, expiration date and storage history, and concrete temperature where it sits outside normal room temperature, because working time and cure time move with it.
- Anchor element free of bond-interfering substances, threads undamaged, rebar free of loose rust.
- Initial adhesive from each new cartridge dispensed to waste, mixing confirmed, injection per the instructions, watching for air entrapment — spring-back or popping as the element goes in.
- The anchor true to its intended angle and secured against movement until fully cured, with final embedment verified from the protruding length and adhesive approximately flush with the surface.
- Proof loading only after the minimum cure time has elapsed.
Three of those — cleaning, hole condition and cure temperature — are what actually go wrong, and none leaves a mark an engineer can find later. That is the whole argument for a witness.
What Calgary adds: temperature and water in the hole
The base material sets the clock, not the air. Working time and cure time follow the temperature of the concrete being drilled, and the task lists require the product be verified as suitable for the concrete temperature on site. A chinook that puts the air at 8 °C above a slab that has sat at −5 °C for a week has not changed the slab. On winter retrofits, somebody measures the concrete.
A wet hole is a different product. The adhesive must be verified as suitable for the actual hole condition — dry, water-filled, submerged or overhead. A core hole that fills overnight is not what most data sheets assume, and that verification belongs to whoever selects the product, before a crew is standing there with a cartridge.
Post-installed rebar dowels sit in the same clause
If you are doweling into existing concrete to tie a new slab, wall or footing to an old one, you are not outside this. The Canadian clause names post-installed rebar alongside adhesive anchors in the same inspection table, with the same orientation and sustained-tension trigger. Doweling horizontally into an existing wall to carry a permanent load is exactly the condition that draws continuous inspection and proof loading — so price it that way. A detail that looked like half a day of drilling can carry an inspector, a calibrated ram and a test program with it.
Where the City of Calgary comes into it
Alberta’s permit system does not use the term “special inspection” the way the American code does. What it has is professional involvement and field review, and the City can require both based on complexity.
City of Calgary Building Advisory B23-010, Professional Involvement Based on Complexity (May 20, 2025) cites the National Building Code 2023 Alberta Edition, Division C sentence 2.4.1.1.(4) — the provision for projects whose size or complexity may give rise to special safety concerns. Where it applies, the City may require registered professionals, and a coordinating registered professional, to authenticate drawings and to perform field reviews, even where building area or dwelling unit count would not otherwise trigger them. Its examples include additions, second storeys and mezzanines added to an existing building, changes of occupancy, and alternative solutions.
To be straight about that document: it does not mention anchors. It is the mechanism by which a field-review obligation can land on a retrofit, and work that hangs new permanent load off old concrete is the kind that attracts one. Whether the anchor inspection and the field review are one person’s job is a question for your structural engineer and the Planning Services Centre.
FAQ
Does every adhesive anchor need continuous inspection? No. Continuous special inspection and proof loading attach to adhesive anchors and post-installed rebar installed horizontally or upwardly inclined and resisting sustained tension. Other adhesive anchors, and mechanical anchors, get periodic special inspection.
Can our site superintendent be the special inspector? Generally no. Inspection is performed by a third party, or by someone employed by the owner or the owner’s representative with the necessary competence.
What load does a proof test use? The lesser of 67 per cent of the characteristic bond resistance in uncracked concrete and 80 per cent of the minimum specified yield of the anchor steel, held a minimum of 10 seconds in a confined test setup. American guidance for the same test asks at least 15 seconds — use the figure your specification names.
Who decides how many anchors get tested? Your contract documents. The Canadian clause puts the testing program there rather than publishing a percentage, so silence means the percentage has not been set. Passing a proof load also does not let anyone skip the inspection — the clause says so directly.
Where this article stops
This is a documents-and-inspection article. It gives no capacity values, embedment depths, edge distances or spacing — those come from the evaluated data for the specific adhesive and from your structural engineer. It does not interpret CSA A23.3 clause by clause, and it does not cover whether the existing concrete can accept the load or how to find the steel you are about to drill into. For that, start with non-destructive concrete testing and the structural checks in cutting openings in an existing slab.
Talk to us before the holes are drilled
The expensive version of this conversation happens after the connection is installed, when somebody asks for a test program nobody wrote and a witness nobody engaged. The cheap version happens at the pre-construction meeting, over a drawing.
Bring us the detail and the specification for your Calgary retrofit. We will walk the anchor schedule, flag the installations that draw continuous inspection and proof loading, and tell you what the drilling and coring needs — see concrete cutting and coring in Calgary. If the connection is cast-in instead, that is a tolerance conversation: start with anchor bolt setting tolerances.
Sources
- Construction Canada — Quality assurance of post-installed anchors in CSA A23.3-24 — published summary of the Annex D inspection table, continuous and periodic definitions, proof load limits, hold time, remediation plan and inspector requirements
- ACI — Job Task Analysis, Post-Installed Concrete Anchor Installer and Inspector (CP-80 task list) — drilling, cleaning, adhesive expiry and mixing, gel and cure time, embedment verification, suitability for hole condition and concrete temperature
- Concrete Anchor Manufacturers Association — Special Inspection Guidelines for Post-Installed Anchors — continuous and periodic definitions, inspector qualification and employment, adhesive anchor checklist, proof load sampling rates and hold time
- City of Calgary Building Advisory B23-010 — Professional Involvement Based on Complexity — National Building Code 2023 Alberta Edition Division C 2.4.1.1.(4), field review, and the complexity examples